| Types of Applications |
Duration
|
| Changing of Land Conditions |
6 months
|
|
|
6 months
|
| Land Mortgage |
6 months
|
| Extend of Land Lease |
6 months
|
| Land Modification |
12 months
|
| Land Temporary Occupancy Licenses (TOL) |
6 months
|
| Access Road Permissions |
3 months
|
| Land Acquisition |
18 months
|
| Continue Temporary License |
1 month
|
| Process of requesting Electricity / Water supply |
1 week
|
Constructing of houses/building for Land
Outside the control area |
3 weeks
|
Permission to Carry out Earthworks (To Demolish / Level / Burrow) for Land
outside the Control Area |
1 week
|
| Land Grant Registration |
2 weeks
|
| Land Grant replacement (damaged/lost grant) |
1 week
|
| Land Grant amendment (name/names) |
1 week
|
| Transmission of land Ownership |
1 week
|
| Land replacement |
12 months
|